Projects

For details about a project, click on a title below.

Ridgewood Park Subdivision - Phase I at Waterways Township

Approximate Contract Amount
$1,545,000

Description
Clearing, grading, installation of storm water and sanitary distribution systems, concrete curbing and roadway paving of subdivision in Richmond Hill, Georgia. (Completed February 2011)

Customer
Savannah Land Holdings, LLC
http://www.sunbeltholdings.com/Pages/waterways.html

Rice Creek Subdivision - Phase II

Approximate Contract Amount
$735,000

Description
Grading and installation of new water, sewer, and storm drainage system; curb and gutter; and paving for 89-lot subdivision in Port Wentworth, Georgia. (Completed April 2010)

Customer
Fred Williams Home
http://www.fredwilliamshomes.com/

Health & Human Sciences Building

Approximate Contract Amount
$335,000

Description
Grading; demolition of existing parking lot and drainage; installation of new water, sewer, and storm drainage systems; installation of new parking lot and brick pavers at Georgia Southern University, Statesboro, Georgia. (Completed June 2010)

Customer
Garbutt/Christman (joint venture)
http://www.garbuttconstruction.com
http://www.christmanco.com

Willow Point Subdivision - Phase 4A

Approximate Contract Amount
$580,000

Description
Clearing; grading lagoons and roadways; installation of water, sewer, and storm drainage system; and paving roadways in Willow Point.. (Complated November 2010)

Customer
Landmark 24 Development
http://www.landmark24.com

Twin River Road Improvements

Approximate Contract Amount
$530,000

Description
Grading, clearing, underground utility demolition, installation of new storm sewer system, curb and gutter, and asphalt base and paving in Midway, Georgia. (In Progress)

Customer
Liberty County, Georgia
http://www.libertycountyga.com/

Lake Shore Subdivision

Approximate Contract Amount
$435,000

Description
Grading and installation of new water, sewer, and storm drainage system; curb and gutter; and paving for 55-lot subdivision in Port Wentworth, Georgia. (In Progress)

Customer
Fred Williams Home
http://www.fredwilliamshomes.com

Industrial Electro Mechanical Building

Approximate Contract Amount
$58,000

Description
Clearing, demolition of existing concrete building pads, placing new building pads, storm sewer, and new asphalt parking lot. (Completed October 2010)

Customer
Joe Marchese Commercial Construction
http://www.joemarcheseconstruction.com

FedEx Parking and Driveway Expansion

Approximate Contract Amount
$86,570

Description
Grading, de-mucking, concrete and asphalt parking lot construction in Savannah, Georgia. (Completed November 2010)

Customer
Pioneer Construction
http://www.pioneersavannah.com

Bellville Agri-Solutions Fertilizer Plant

Approximate Contract Amount
$185,000

Description
Grading; installation of water system, storm drainage; remediation of unsuitable soils; and placing gravel roadways and parking areas in Bellville, Georgia. (Completed March 2010)

Customer
Bland Farms
http://www.blandfarms.com